Depending on the scope of your project, you may need to pass specific inspections to ensure everything meets City standards. While not every project requires every inspection, please see the list below for potential inspections that may be needed.

Scheduling Inspections

Use ePlace to schedule inspections online or call 913-895-6220. You can schedule inspections for the next day or for future dates between 8 a.m. and 4 p.m. Please note that not all inspections allow for a specific appointment time.

Inspection Status

  • Partial Pass: The inspection meets requirements, but allows the same inspection to be requested again.
  • Reinspection Required: The inspection did not pass. Make the required changes before the next inspection.
  • Partial Pass – TCO Ready: There are still outstanding items remaining on the project, but Temporary Occupancy is permitted.
  • Passed: The inspection passed and is fully approved.

Foundation Inspections

One-hour appointment times available 9 a.m.-3:15 p.m.

Call the inspector for any cancellations or changes.

Footing + Piers

The City must inspect forms, trenches and all reinforcing steel before you pour concrete. The City does not inspect footings for uncovered decks, but you must install them according to code and at least 36 inches below finished grade. Schedule inspections at least one day before your planned concrete pour. The City of Overland Park does not accept third-party inspections as a substitute for inspections performed by City staff.

Structural Wall

Inspection of reinforcing steel installation and size in concrete walls, also referred to as foundation wall or stem wall, before pouring.

Structural Column

Inspection of reinforcing steel placement and size in concrete columns before pouring concrete.

Slab Insulation

Inspection of insulation installed under the concrete slab or along the foundation wall is required for all one- and two-family dwellings, townhomes, room additions and four-seasons rooms using the Prescriptive or Local Prescriptive energy paths.

Structural Slab

Inspection of reinforcing steel placement and size in concrete floors before pouring concrete.

Vapor Barrier

For basements and garages, before pouring concrete.

Framing Inspections

Structural Braced Wall + Shear Wall

Inspection of anchoring devices and nailing patterns for lateral braced walls or shear walls.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Sheetrock

Inspection of the tile backer, fire-rated walls and garage sheetrock prior to taping and mudding.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Porch Framing

Inspection of the covered porch frame prior to the ceiling being installed.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Residential Rough-In

General inspection of structural components, electrical wiring, plumbing (drainage and water) and mechanical work during the rough-in stage, before insulation and drywall are installed.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Commercial Rough-In

Inspection of foundational aspects of your project, including electrical wiring, plumbing systems, mechanical work and structural items. While most often used for apartment complexes, we may require this same inspection for other commercial work. Inspectors will also review the weather-resistant barrier at this stage.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Insulation

Inspection of R-value of insulation in walls, ceilings and rafters and proper ventilation. Venting of the rafter space can be inspected during the residential rough-in.

Next-day inspections occur between 8 a.m. and 4 p.m. Although appointments are not available, you may request a morning or afternoon time preference for occupied homes.

Lath-Stucco

Inspection of the weather barrier and how the metal lath is attached prior to stucco application.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Flashing

Inspection of residential doors and windows prior to siding installation.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Above Ceiling

Inspection of the electrical, plumbing and mechanical systems that are installed above the ceiling prior to the ceiling being installed. This inspection cannot be scheduled until your fire sprinkler and alarm plans have been approved.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments are not available, but you may request a morning or afternoon time preference for occupied homes.

Fire-Resistive Wall + Column

Inspection for proper materials and installation of fire-rated assemblies, including rated walls, ceilings, columns and floors. If the assembly uses drywall materials, the inspection must be made before mudding and taping. If multiple layers are involved, each layer must be inspected before proceeding to additional layers or applying finish materials.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Fire-Resistive Ceiling/Horizontal Assembly

Inspection of either a floor/ceiling assembly or a roof/ceiling assembly is required to have a fire rating. The inspector will examine the nail or screw pattern. This is done after the rough-in inspection or the above ceiling inspection.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Electrical Inspections

Next-day inspections occur between 8 a.m. and 4 p.m.

You may request a morning or afternoon time preference for occupied homes.

Electrical Service + Clearance

Upon approval of the electrical service inspection, clearance of the service is automatically forwarded to the power company the next business day. If the house is occupied, the clearance can be called in on the same day. 

 

Electrical - Wall

A rough-in inspection of wiring and other electrical components located within a wall.

Electrical - Emergency Generator

This inspection involves the operational testing of an on-site emergency generator.

Electrical Conduits (Concealed)

Inspection of the electrical conduits inside the building and exterior on the site, routing, size and support before covering, obstructing from view or embedding in masonry or other material.

Electrical - Pool/Spa Bonding

Inspection prior to pouring concrete to verify that all of the required pool shells, decks, metallic parts of the pool and the body of water are electrically bonded, including reinforcing bars (fiberglass and encapsulated reinforcing bars are not allowed for this use) in the concrete for the pool walls, bottom, deck, diving boards, ladders, handrails, fixtures for pool lights, electrical conduits and metal fences.

Electrical Seal Off for Fuel Dispensing

Inspection of the electrical seal-offs at the perimeters of hazardous classified locations.

Plumbing Inspections

Next-day inspections occur between 8 a.m. and 4 p.m.

You may request a morning or afternoon time preference for occupied homes.

Ground Rough

Inspection of the under-slab plumbing lines prior to the slab being poured. A pressure test is required on commercial projects.

Top Rough

Inspection of all plumbing lines located in the walls or ceiling prior to covering with drywall or ceiling finish materials. Drainage and vent lines must be pressure tested.

Roof Drain

Specific inspection of the roof drainage system, either above or below ground, or both. The drain lines must be pressure tested.

Storm Drain

The Inspection of plumbing lines for the storm drains, either under the slab inside the building or underground outside the building. The lines inside the building must be pressure tested. 

Private Sewage Disposal + Septic/Holding Tank

The Johnson County Department of Health and Environment permits and inspects septic systems. For more information, visit the JCDHE website.

Mechanical Inspections

Gas Line Test + Fuel Gas Service Clearance

Inspection of the product lines and witnessing of an air or soap test to ensure that the pipe holds the proper test pressure must be completed before covering. Upon approval of the inspection, clearance of the service is automatically forwarded to the power company the next day. If the house is occupied, the clearance can be called in the same day.

Next-day inspections occur between 8 a.m. and 4 p.m. Although appointments are not available, you may request a morning or afternoon time preference for occupied homes.

Mechanical Duct Detector Test

Performance testing of smoke detectors located within the air handling unit.

Next-day inspections occur between 8 a.m. and 4 p.m. Although appointments are not available, you may request a morning or afternoon time preference for occupied homes.

Fuel Dispenser

Inspection of the product dispenser installation, including the anchorage and shear valves.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Fuel Tank

Inspection and air or soap test of the tanks before setting in the ground. There may also be an inspection of the tank pad before pouring the concrete footing or anchoring the tank after installation to ensure proper support and corrosion protection.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Fuel Lines (Product Stations)

Inspection of the product lines and witnessing of an air or soap test prior to being covered.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Fire Protection Inspections

Fire Suppression - Hydrostatic Test

The hydrostatic testing of a fire line.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable. Call the inspector for any cancellations or changes.

Fire Suppression - Hood and Duct

Inspection of the hood and duct system and testing of the proper operation of all associated mechanical equipment. The installer performs the test in accordance with the manufacturer’s requirements, the code requirements and in view of the inspector. The test may include electrical functionality, fuel shut-off and dispersal of test gases through the piping system, among other aspects.

One-hour appointment times available 9 a.m.-3:15 p.m.

Call the inspector for any cancellations or changes.

Flow Test Standpipe

Inspection to witness the flow of the standpipes to verify the proper rate of the flow and pressure as required by the building code for the particular building involved. The test is performed by the installer and witnessed by the Building Inspector and personnel from the Overland Park Fire Department. Standpipes are to be installed during construction on buildings requiring them.

Next Day: One-hour appointment times available 9 a.m.-3:15 p.m.

Call the inspector for any cancellations or changes.

Fire Line - Visual

The visual inspection of a wet or dry fire protection system. No test is performed.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable.

Fire Line - Hydro

Inspection of the inside wet fire suppression system lines and the witnessing of a 200 psi hydrostatic pressure test for a minimum of two hours. All sprinkler heads should be in place and cut sheets of special heads should be on site. The same designation is used to schedule inspections for a dry system, but the testing uses 40 psi of air pressure for 24 hours.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable. Call the inspector for any cancellations or changes.

Fire Line - Flush

Inspection of the flushing of the underground fire suppression lines to ensure proper debris removal prior to connecting to the inside building standpipes or sprinkler system. The installer will flush the system to the inspector’s satisfaction at the required rate of 10 feet per second, as per NFPA Standards.

Next-day inspections occur between 8 a.m. and 4 p.m. Appointments unavailable. Call the inspector for any cancellations or changes.

Fire Alarm - Test

The complete testing of an alarm system within a building, including smoke detectors and pull stations. Typically, this inspection is scheduled in conjunction with a final inspection or immediately prior to it. This inspection cannot be scheduled without approved fire alarm plans.

Next Day: One-hour appointment times available 9 a.m.-3:15 p.m.

Call the inspector for any cancellations or changes.

Fire Pump - Test

Inspection includes the complete performance testing of a fire pump, including the flow of standpipes, the pressure produced by the pump and the arrangement of the pump’s power supply.

Next Day: One-hour appointment times available 9 a.m.-3:15 p.m.

Call the inspector for any cancellations or changes.

Site Inspections

Building Safety Erosion + Sediment Control

Inspection of the erosion and sediment control measures, usually on single-family lots. Scheduled by City staff, as needed.

Building Safety Erosion Control Complaint

Inspection documenting the response to a complaint that has been received related to erosion control measures. Scheduled by City staff, as needed.

Engineering Services Erosion & Sediment Control

Inspection of erosion and sediment control measures on nonresidential sites. Next-day inspections occur between 8 a.m. and 4 p.m.  Applicant schedules initial inspection after installing perimeter controls and before beginning land disturbance. City staff scheduled subsequent inspections on a periodic basis.

Engineering Services Form Inspection

Form inspection for residential and commercial drive approaches prior to placing concrete. For new single-family residences, this includes: driveways (slope and subgrade checks), sidewalks and ramps (slope and subgrade checks) and verifying reinforcement when required. For commercial sites, this includes sidewalks and ADA ramps (slopes and subgrade checks).

Same-day appointments available. Please note the time of the call. Inspections called in after 3 pm will be scheduled for the next business day. For commercial projects, call your assigned ES Inspector directly to schedule a form inspection.

Provide the flatwork subcontractor’s name and phone number. Once scheduled, the inspector will respond within four hours.

Engineering Services Final Site Grade

The inspection of swales, berms, drainage components, sidewalks, paved areas, as well as overall compliance with the approved site plan. Next-day inspections occur between 8 a.m. and 4 p.m.

Engineering Services Storm Sewer

Inspection of private storm sewer installation. Inspection involves verifying the materials used for pipes, ensuring proper joint connections and confirming the pipe bedding.

Contact the Engineering Services inspectors to schedule.

Engineering Services Project Inspection

This inspection activity is used to document any site visit performed for general reasons, including those in response to questions from contractors and will also be used in the future to document Sanitary Sewer backfill inspections in the public street right-of-way, previously performed under the LDP permit.

Contact the Engineering Services inspectors to schedule.

Engineering Services Final Inspection

Final Inspection prior to Certificate of Compliance. Items checked include:

  • ADA ramp slope
  • ADA stalls
  • Pavement conforms with the overall approved plan
  • Sod/landscape installed
  • Site stabilization and removal of BMPs (no check of landscape materials).
  • Verify that the site is constructed in accordance with the approved city plan.

Next-day inspections occur between 8 a.m. and 4 p.m.

Other Inspections

Elevator

New installations only. Testing the fire service and inspecting the hoistway and shaft penetrations.

Inspection must be scheduled. One-hour appointment times available between 9 am and 3:15 pm.

The Kansas State Fire Marshal enforces regulations relating to elevators and their operation.

Miscellaneous

For a nonstandard item, a description is typically entered in the inspection form’s remarks area.

Final Inspection

 

All permits require a final inspection of all completed work prior to the issuance of an Occupancy Permit or a Certificate of Compliance. This inspection is also a prerequisite for a Temporary Certificate of Occupancy. Please schedule the appropriate final inspection based on your project.

Certificates of Occupancy

Temporary Certificate of Occupancy

A final inspection is required prior to issuing any Temporary Certificate of Occupancy. Once a TCO has been issued, you may see a TCO inspection scheduled. This inspection verifies if all the items listed on the TCO are complete. If so, the project will receive a permanent Certificate of Occupancy. To receive a TCO, please schedule a final inspection and note your request in the inspection comments.

Certificate of Occupancy + Compliance

After a final inspection is approved, a Certificate of Occupancy/Certificate of Compliance will be emailed to the applicant, closing out the permit. To receive a CO, please schedule a final inspection.