Road Construction/Stormwater Projects

Each year, the city completes a number of road construction and public improvement projects. The design and construction of these projects such as thoroughfares, residential streets, bridges, traffic signals and storm water drainage are paid for with money dedicated to the Capital Improvements Program.

The benefits of these projects are significant including safety and better traffic movement. Occasionally, there will be some traffic delays and temporary disruptions. Before departing, check out the city's traffic web cameras and interactive Road Closure Map.

Maintenance of city streets and addressing traffic flow on major streets are two of the top three priorities listed by respondents to a citywide survey.

 Road Improvements | Stormwater Projects

2016 Neighborhood Street Reconstruction Program
Project manager: Becky Bonebrake, 913-895-6008

2016 NSRP project location mapThe project is located at 71st and 73rd streets, between Metcalf and Lamar avenues. The improvements include new pavement, sidewalk, curb, gutter, sidewalks and stormwater improvements. Construction is expected to begin spring 2016. The streets will be closed to through traffic; and residents will have access tot their property over temporary gravel.

Construction will begin March 2016 and is expected to be completed in late 2016.

Public Safety Facility
Project manager: Brian Scovill, 913-895-6052

new public safety facilityOverland Park will construct a new Public Safety Facility at 163rd and Antioch across from the Blue Valley West High School's campus. This jointly occupied facility will serve both the Police and Fire departments. The building is 23,500 square feet and has been designed to meet the current and future needs of both departments. The building, which is 23,500 square feet, will house the Overland Park Police Tactical Operations Unit on one side and the other will be for the Fire Department's crew of 12, with four double deep apparatus bays.

Construction should start April 2015. The facility will be complete and in service in the summer of 2016.

159th Street, Nall Avenue to Mission Road
Project manager: Tony Rome, 913-895-6001

159th Street Nall to Mission avenuesProposed improvements include reconstruction of 159th Street, from Nall Avenue to Mission Road to thoroughfare standards, including a roundabout at the Mission Road intersection. Other improvements include sidewalks, a multi-use trail, streetlighting, storm sewers and restoration.

Utility relocation is underway and construction is scheduled to begin in mid 2016.

159th Street, Metcalf to Nall avenues
Project manager: Eric Keenan, 913-895-6028

159th Metcalf Nall renderingThe proposed improvements include reconstruction of 159th Street, from Metcalf to Nall avenues to thoroughfare standards that include sidewalks, bike trail, street lighting, traffic signal at 159th Street and Nall Avenue and roundabouts at the east and west entrances to Blue Valley High School.

Utility relocation is in progress and construction is scheduled to begin late 2015.

Switzer Road, College Boulevard to Indian Creek Parkway
Project manager: Brian Scovill, 913-895-6052

Construction of Switzer Road, from the Indian Creek Bridges to College Boulevard will include two round-a-bouts. One of the round-a-bouts will be located at Indian Creek Parkway and the other at the proposed 113th Street. Other improvements will include a signal at College Boulevard, considerable landscaping and two art features located within the round-a-bouts. This project will require the removal of the existing Switzer roadway and realignment to support the proposed City Place Development. This $350,000,000 mixed-use development will be located at the southwest corner of College Boulevard and U.S. Highway 69.

Construction is anticipated to begin April 2015. It should be open to traffic by November 2015, with final restoration in spring, 2016.

Stormwater Projects

92nd Place and Switzer Road Storm Sewer Improvement
Project manager: Charlie Love, 913-895-6193

Photo for 92nd place and SwitzerThis project will improve and enhance aging and deteriorating storm sewer inlets, storm sewer pipe and concrete ditch liners in the area. This will be done in order to ensure the efficient conveyance of storm water as well as to address flooding concerns. These storm sewers are generally located in the back yards of properties west of Switzer Road, between 91st and 95th streets.

In addition, this project will include complete reconstruction of Switzer Road, from 91st to 95th streets. These improvements include new pavement, curb and gutter, sidewalks and stormwater.

In December 2014, V.F. Anderson Builders began work on the existing storm sewers; these locations will be completed and restored by May 2015. Work along Switzer Road will begin spring 2015 and will be completed by November 2015.

103rd and Connell Flood Control Project
Project manager: Tony Rome, 913-895-6001

103rd & Connell Stormwater ProjectThis project will improve and enhance the existing tributary of Indian Creek upstream and downstream of 103rd Street and Connell. This will alleviate flooding of more than 20 homes and adjacent roadways during large storm event.

The 103rd Street bridge is now open to through traffic in both directions, with daily lane closures to complete the project's restoration.

Improvements included replacement of the existing reinforced concrete box (RCB) with a triple-span bridge, widening and deepening of the channel and restoration of adjacent properties.

Construction is underway and is scheduled to be completed in late 2015.

Stanley Storm Drainage Improvements, 151st Terrace and Metcalf Avenue
Project Manager: Eric Keenan, 913-895-6028

This project involves installing approximately 1,500 linear feet of reinforced concrete box to enclose the Negro Creek system from Metcalf Avenue to the east end of the Stanley Industrial Park. These improvements will replace the existing natural channel and remove the adjacent areas from the 100-year floodplain. The project will require a detour of the private drive section of Broadmoor Street, with no interruption to traffic.

The project is scheduled to begin May 2015 and an estimated completion date of March 2016.

Monitor Square Storm Drainage Improvements
Project Manager: Lorraine Basalo, 913-895-6023

Monitor SquareThis project will improve and enhance an existing tributary of Indian Creek upstream of 103rd and Rosewood streets. This will alleviate flooding of several homes and roadways during large storm events. The improvements include channel and overbank grading, replacement of an existing reinforced concrete box (RCB) with a single-span bridge, and the realignment and upsizing of existing sanitary sewers.

Construction is scheduled to commence as early as mid-November 2015. Improvements will be substantially complete in June 2016, with fall restoration being completed by December 2016.